Protective Coating Maintenance IDIQ
AI Overview
Seeks a contractor to perform protective coating maintenance across Air Force facilities, including exterior and interior painting, pavement markings, floor and pool coatings, and signage. Work is delivered through task orders on an indefinite-delivery basis, keeping base infrastructure protected and maintained.
This summary is AI-generated from the official solicitation.
Key Details
Official Description
--- Attachment text --- [Solicitation_Amendment_FA302026Q01040001_SF_30.pdf] AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
- CONTRACT ID CODE J PAGE 1 OF 2
- AMENDMENT/MODIFICATION NUMBER 0001
- EFFECTIVE DATE 14 Oct 2026
- REQUISITION/PURCHASE REQUISITION NUMBER
- PROJECT NUMBER (if
applicable) 1 6. ISSUED BY CODE FA3020 FA3020 82 CONS LGC 206 J AVE BLDG 1662, CP 940 676 2663 SHEPPARD AFB, TX 76311-2743 UNITED STATES ASHLEY GREEN, Email: ashley.green.18@us.af.mil Telephon...
Change History
Critical change · Description + Submission + Deadline + Attachment
Protective Coating Maintenance IDIQ
- Purpose of the amendment: Amendment 0001 (dated 14 Oct 2026, signed 16 Oct 2026) was issued only to answer vendor questions; the notice states no other changes were made to the solicitation.
- Solicitation number and attachments: The solicitation number changed from FA302026Q0104 to FA302026Q01040001 on the amendment form, and Attachment 08 (Amendment 1 Questions and Answers) was added.
- Clause added: FAR 52.228-15 (Performance and Payment Bonds, Construction, Jun 2020) was added to the contract clauses.
- Key Q&A clarifications for pricing:
- Offerors must price using the Government's estimated quantities in Attachment 02 (Price Exhibits A–E); no historical job-order data is available.
- No minimum job order value beyond $1.00 under FAR 52.216-19; there is no separate line item for mobilization, demobilization, supervision, setup, or equipment transport, so these costs must be built into fully burdened unit prices.
- Exterior painting above 25 feet anticipates working heights of 25 to 60 feet, with all access equipment included in prices.
- If a boom lift or other powered equipment can't be placed at a site, the work order may be mutually retracted.
Why it matters: Bidders should revise pricing to fully burden small orders and high-elevation work, and confirm bonding readiness given the new FAR clause.
Protective Coating Maintenance IDIQ
New opportunity: Protective Coating Maintenance IDIQ
Similar Opportunities
Get Alerts for Opportunities Like This
RallyProp monitors thousands of funding sources and sends instant alerts when opportunities match your technology and capabilities.
Start Free Trial