RIO DE LA PLATA FLOOD CONTROL PROJECT, SUPPLEMENTAL CONTRACT 1 PROJECT LOCATION: DORADO AND TOA BAJA, PUERTO RICO

Department of DefenseW2SR TF VIPR

AI Overview

This amendment updates a levee construction contract for flood control in Dorado and Toa Baja, Puerto Rico, revising bid items and fill quantities. It addresses stage-construction requirements and clearing and grubbing procedures for a standard civil works project.

This summary is AI-generated from the official solicitation.

Key Details

Agency
Department of Defense
Funding Amount
—
Release Date
September 3, 2026
Due Date
October 27, 2026

Official Description

--- Attachment text --- [Solicitation_Amendment_W51DQV26RA0020005_14Oct2026.pdf] AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

  1. CONTRACT ID CODE J PAGE OF PAGES 1 3
  2. AMENDMENT/MODIFICATION NUMBER 0005
  3. EFFECTIVE DATE 14 OCT 2026
  4. REQUISITION/PURCHASE REQUISITION NUMBER
  5. PROJECT NUMBER (If applicable) K8P0100
  6. ISSUED BY CODE W51DQV
  7. ADMINISTERED BY (If other than Item 6) CODE

W2SR ENDIST CARIBBEAN(PROVIS) 383 FRANKLIN D ROOSEVELT AVENUE, SAN JUAN SAN JUAN...

View on official source

Change History

Description ChangedOct 14, 2026 at 6:39 PM

Critical change · Deadline + Requirements + Scope + Attachment + Funding + Description

RIO DE LA PLATA FLOOD CONTROL PROJECT, SUPPLEMENTAL CONTRACT 1 PROJECT LOCATION: DORADO AND TOA BAJA, PUERTO RICO

  • Amendment 0005 replaces the prior amendment's scope in several areas, mainly the Rio de la Plata Supplemental Contract 1 levee work.
  • Levee fill bid items split into East and West: a new East Levee Fill CLIN 0019 (548,864 cubic meters), an East Levee Common Fill CLIN 0021 (1,063 cubic meters), and an East Levee Select Fill CLIN 0023 (12,019 cubic meters) were added. West Levee Fill (CLIN 0020) was cut from 771,895 to 223,031 cubic meters, Common Fill from 800,422 to 799,359, and Select Fill from 18,361 to 6,342.
  • CLIN renumbering: former CLINs 0022 through 0084 shift up three positions, ending at CLIN 0087, so pricing references must be updated.
  • Stage-construction right reserved: Section 35 41 00 now lets the Government change stage-construction requirements, including fill placement rate, pending review of additional technical data, with equitable adjustment possible by modification.
  • Clearing, grubbing, and stripping narrowed: payment is limited to work within permanent excavation, channel, structure, and embankment footprints. Staging areas, storage yards, haul roads, and similar Contractor-convenience work are now incidental and unpaid. A Clearing and Grubbing Plan needs Government approval before site disturbance.
  • Section 01 00 specs updated: Sections 01 33 00 and 01 45 00 are replaced with UFGS versions, and UFGS 01 45 00.25 10 is added.
  • Proposal due date moved from 15 Sep 2026 (in the earlier amendment) to 27 Oct 2026 at 2:00 p.m. San Juan time.

Why it matters: Pricing must be rebuilt around the East/West split and new CLIN numbers, and bidders should price clearing as footprint-limited, with staging and access costs absorbed elsewhere.

Description ChangedSep 22, 2026 at 6:05 PM

Informational change · Description

RIO DE LA PLATA FLOOD CONTROL PROJECT, SUPPLEMENTAL CONTRACT 1 PROJECT LOCATION: DORADO AND TOA BAJA, PUERTO RICO

Description information changed.

Opportunity AddedSep 21, 2026 at 11:23 PM

RIO DE LA PLATA FLOOD CONTROL PROJECT, SUPPLEMENTAL CONTRACT 1 PROJECT LOCATION: DORADO AND TOA BAJA, PUERTO RICO

New opportunity: RIO DE LA PLATA FLOOD CONTROL PROJECT, SUPPLEMENTAL CONTRACT 1 PROJECT LOCATION: DORADO AND TOA BAJA, PUERTO RICO

Similar Opportunities

Get Alerts for Opportunities Like This

RallyProp monitors thousands of funding sources and sends instant alerts when opportunities match your technology and capabilities.

Start Free Trial