Request for Offer for RADMAC III Parcel E Remedial Action

Department of DefenseNAVFACSYSCOM SOUTHWEST

AI Overview

This Navy solicitation seeks a contractor to carry out remedial action at Parcel E of Hunters Point Naval Shipyard, including groundwater treatment, shoreline excavation, slurry wall work, and munitions-and-explosives support. It is an environmental cleanup and construction services effort rather than a technology development opportunity.

This summary is AI-generated from the official solicitation.

Key Details

Agency
Department of Defense
Funding Amount
—
Release Date
September 21, 2026
Due Date
October 13, 2026 (Closed)

Official Description

--- Attachment text --- [Amendment_04_N62473_26_R_B_009_KO_Signed.pdf] AMENDMENT 04 – 08 OCTOBER 2026

CONTRACT: N62473-24-D-0004 Title: Parcel E Remedial Action, Hunters Point Naval Shipyard, San Francisco, California. PTO: N62473-26-R-B-009 CS/Phone: Ilana Feliu, Phone: (619) 524-5490 Solicitation Date: September 02, 2026 Subject: Amendment to the Request for Proposal

THE PURPOSE OF THIS AMENDMENT IS TO INCORPORATE THE FOLLOWING ANSWERS TO THE REQUESTS FOR INFORMATION RECEIVED FOLLO...

View on official source

Change History

Description ChangedOct 13, 2026 at 5:41 PM

Material change · Requirements + Scope + Description

Request for Offer for RADMAC III Parcel E Remedial Action

  • Amendment 04 replaces Amendment 03's content entirely. Amendment 03 only extended the proposal due date (October 13 to November 3, 2026); Amendment 04 instead publishes answers to site-visit RFIs for Parcel E remedial action at Hunters Point Naval Shipyard.
  • Key scope clarifications added:
    • Ten monitoring wells at IR-03 must be installed; a Remedial Action Monitoring Plan is provided, with the contractor to use best judgment on well details.
    • Additional excavation may be required, with PPI 3 (Additional Excavation and Backfill) likely used and estimates to be provided by offerors.
    • Hybrid revetment work must be completed north and south of the armored revetment, and about 1,800 linear feet of concrete seawall is to be estimated.
    • IR-03 slurry wall backfill is cement-bentonite, not soil-bentonite.
    • UXO support includes anomaly investigation, MEC identification, MPPEH evaluation, and explosives-safety-status determinations.
  • Bonding requirement: Both payment and performance bonds at 100% of project value are required.
  • Submission changes: The Offer Schedule must be submitted as both signed PDF and Excel; Factors 1 and 2 plus the Gantt chart must be a single PDF; figure pages now count toward the four-page limit.
  • Why it matters: Applicants must price the estimated well, excavation, revetment, and seawall quantities, budget for full bonding, and follow the revised single-file format.
Description ChangedOct 5, 2026 at 6:39 PM

Informational change · Description

Request for Offer for RADMAC III Parcel E Remedial Action

  • Proposal due date extended three weeks: Amendment 03 (Oct 5, 2026) moves the deadline from October 13, 2026, 2:00 PM PDT to November 3, 2026, 2:00 PM PST. Offerors get extra time to prepare.
  • Amendment 02 Q&A removed from the description: The attachment text now shows only Amendment 03. The Amendment 02 answers and the Remedial Action Monitoring Plan attachment no longer appear. Those answers still apply, since "all other terms and conditions remain unchanged." They covered:
    • 4-page limit, with figures counted inside it
    • Gantt chart on up to two 11x17 sheets
    • Technical Approach weighted twice as important as Local Hiring
    • No bid bond
    • 90-day offer validity
    • Follow the 2019 RAWP for trench and key dimensions
    • Exploratory borings required in the ISS area
  • Reminder: Offerors must acknowledge all amendments on the Offer Schedule. Failure to do so may get the proposal rejected.
  • The notice remains limited to RADMAC III contractors. The description also now includes a short notice summary and the contact for Ilana Feliu.
Description ChangedSep 22, 2026 at 5:57 PM

Critical change · Deadline + Description + Submission

Request for Offer for RADMAC III Parcel E Remedial Action

Amendment 02 officially confirms the proposal deadline as October 13, 2026, and clarifies that this RADMAC III task order is exclusive to RADMAC III contractors.

Opportunity AddedSep 21, 2026 at 11:22 PM

Request for Offer for RADMAC III Parcel E Remedial Action

New opportunity: Request for Offer for RADMAC III Parcel E Remedial Action

Similar Opportunities

Get Alerts for Opportunities Like This

RallyProp monitors thousands of funding sources and sends instant alerts when opportunities match your technology and capabilities.

Start Free Trial